It looks like you're using an Ad Blocker.
Please white-list or disable AboveTopSecret.com in your ad-blocking tool.
Thank you.
Some features of ATS will be disabled while you continue to use an ad-blocker.
Originally posted by Doctor Smith
Let's assume the steel re enforced core of the building reached a high enough temperature to collapse. Which is did not.
Lets assume that the steel wasn't welded together which would act as a heat sink drawing the heat away from the hot areas. When in fact they were welded together and it would take a much higher temperature than that required to weaken the steel if it were isolated.
Lets assume the fire was still raging even though a few people were signaling for help from the holes in the building, indicating the fires were almost out. Which wasn't the case.
The building would not collapse in its own foot print. It would fall over in the direction of the weakened area. Following the laws of physics . Following the path of least resistance. Not fall through itself and the strength of solid steel.
Show me one other steel re enforced building that has collapsed that way throughout history?
No architect will agree with this pan cake theory.
video.google.com...#
Show me one other steel re enforced building that has collapsed that way throughout history?
A total of 22 such cases were identified through 2002 after extensive searches of the literature, news, and other contacts, with the Sept. 11 disasters in New York and Washington, DC, counting as five of these incidents [World Trade Center (WTC) 1, 2, 5, and 7, and the Pentagon].
The NIST survey of 22 fire-induced building collapses from 1970-2002 identified a variety of conditions, materials, locations, and buildings. Fifteen cases were from the U.S., two from Canada, and five from Europe, Russia, and South America. The numbers of fire collapse events can be categorized by building material as follows:
Concrete: 7 (1 in Pentagon 9-11 event)
Structural steel: 6 (4 in 9-11 WTC events)
Brick/Masonry: 5
Wood: 2
Unknown: 2
The pre-collapse photographic analysis showed that 16 recovered exterior panels were exposed to fire prior to collapse of WTC 1. None of the nine recovered panels from within the fire floors of WTC 2 were observed to have been directly exposed.
NIST developed a method to characterize maximum temperatures experienced by steel members using observations of paint cracking due to thermal expansion. The method can only probe the temperature reached; it cannot distinguish between pre- and post-collapse exposure. More than 170 areas were examined on the perimeter column panels ...
Only three locations had evidence that the steel reached temperatures above 250 °C.
These areas were:
• WTC 1, east face, floor 98, column 210, inner web,
• WTC 1, east face, floor 92, column 236, inner web,
• WTC 1, north face, floor 98, column 143, floor truss connector
Other forensic evidence indicates that the last example probably occurred in the debris pile after collapse. Annealing studies on recovered steels established the set of time and temperature conditions necessary to alter the steel microstructure. Based on the pre-collapse photographic evidence, the microstructures of steels known to have been exposed to fire were characterized. These microstructures show no evidence of exposure to temperatures above 600 °C for any significant time.
Similar results, i.e., limited exposure if any above 250 °C, were found for two core columns from the fire-affected floors of the towers.
Originally posted by GenRadek
Originally posted by Doctor Smith
Let's assume the steel re enforced core of the building reached a high enough temperature to collapse. Which is did not.
Lets assume that the steel wasn't welded together which would act as a heat sink drawing the heat away from the hot areas. When in fact they were welded together and it would take a much higher temperature than that required to weaken the steel if it were isolated.
...
The Twin Towers' floors were not welded. There were no I-beams holding up the floors. They were trusses. Light steel trusses that were bolted at the ends, connecting to the columns. The core columns were not welded either. Some of the exterior columns were welded at the transfer floors, but the rest of them were not welded either. They were all bolted.
'Composite floors comprise 900mm deep bar joists (spaced at 2.04 m centres and braced transversely by secondary joists) and a 10 cm thick lightweight concrete slab laid on steel trough decking as permanent formwork. Composite action between the concrete and the steelwork is ensured by extending the diagonal web members of the joists through the steel decking and embedding them in the slab. Dead weight of floor 50 kg/in2, imposed load 488 kg/in2.'
'Each upper floor comprises 32 prefabricated units spanning between core and external columns. These units are of two sizes: 18.3 x 6.0 m along the longitudinal faces of the core and 10.7 x 4.0 m along the transverse faces. Additional beams are provided to strengthen the four corner bays.'
It is not clear exactly what the phrase "each upper floor" means in this instance. It turns out that 18 floors have heavy steel beams instead of trusses. Consider the following quote from Engineering News-Record, January 1, 1970.
'On the 41st and 42nd floors, both towers will house mechanical equipment. To accommodate the heavy loads, the floors are designed as structural steel frame slabs. All other floors from the ninth to the top (except for 75 and 76, which will also carry mechanical equipment) have typical truss floor joists and steel decking.'
'Typical office floors have 4-in. thick slabs of composite construction using top chord knuckles of the joists (trusses), which extend into the slab, as shear connectors. On mechanical floors, composite action is provided by welded stud shear connectors...'
...Composite flooring is the name given to floors where studs (called shear studs or shear connectors) are welded to the supporting joists/trusses and then concrete is poured around them, setting them solidly in the concrete slab. The joist-concrete composite slab is significantly stronger than a non-composite slab. In the case of the WTC the main double trusses used their top knuckles as shear connectors. Ordinary shear studs were used along the transverse trusses. We have the following quote from Godfrey:'
...Intact and aircraft impact damaged welds from the exterior columns of the World Trade Center towers were evaluated. The fillet welds joining the various steel plates composing the built-up box columns were primarily deposited using submerged arc welding.
Analysis of the steel to be conducted in both Gaithersburg and Boulder will be done to determine properties and quality of the metal, welds and connections, and to provide data for other investigation projects. This portion of the research will include: