It looks like you're using an Ad Blocker.
Please white-list or disable AboveTopSecret.com in your ad-blocking tool.
Thank you.
Some features of ATS will be disabled while you continue to use an ad-blocker.
Originally posted by exponent
NIST could not verify the as-built construction of WTC7 as WTC7 has been destroyed. Walking round and confirming that welds were up to spec, that plates were correctly fitted, that appropriate bolts were used is not possible because the building no longer exists.
Originally posted by Griff
I have seen what you state. I still think it's a bad design if true. My opinion of course.
Originally posted by Seymour Butz
So what's the verdict?
Would a column buckling prevent connector failure?
Originally posted by Griff
Let's ask Cardington.
In their tests, the connections failed due to tension forming from the cooling of the buckled beams. Not from the buckling itself.
Now, the question becomes: Did NIST take tension caused by cooling into account?
Originally posted by Seymour Butz
Cuz when I think about it, if a column were to buckle, a necessary consequence of that would be a gross misalignment at the connector. Resulting in either bolt shear or a tear-out at the flange.
Originally posted by Griff
Originally posted by Seymour Butz
Cuz when I think about it, if a column were to buckle, a necessary consequence of that would be a gross misalignment at the connector. Resulting in either bolt shear or a tear-out at the flange.
If this where the case, how could one column buckling (column 79) pull the rest of the building down with it? If it's not connected to anything anymore?
It's a catch-22 here.
Originally posted by Seymour Butz
So, if the girder were to buckle, laterally as you suggested, is there something that I'm unable to fathom that would prevent the connector failing?
Also, wouldn't col 79 still be connected to the floors above floor 13? And, wouldn't it still be connected to floors on the other 3 sides? It could pull those down, at least until THOSE connectors failed.
Originally posted by Anonymous ATS
The girders have headed anchor studs welded on top of the beam that makes it composite with the concrete floor deck. This braces it against lateral torsional buckling. It also adds a fair amount of strength.
Originally posted by Griff
1-Not really.
2-But, then again, you have to take into account the whole floor system is connected and not just pieces and parts.
3-Well, the connections either failed OR they were strong enough to pull the remaining floors. Both can not happen. It has to be either one or the other. Because if they were strong enough to pull the remaining floors with it, then the shear load wouldn't be acting on it anymore as the floors would be insync with the connections and not producing any shearing action anymore.
Originally posted by Seymour Butz
I see no scenario whereby the floors above 13 couldn't fall when 79 buckles, leaving the ext columns unbraced and liable to buckling.
Originally posted by Newtons.Bit
I don't follow. Could you explain how a connection would not fail from the member having a thermal expansion of roughly 3 inches?
Originally posted by Griff
Are you saying that the exterior would partially collapse then as they lose their support from east to west unlike what we see in video? Or are you saying until all were unbraced and were allowed to then buckle all nice and neat into themselves at once? Myself, I would imagine the first.
Originally posted by Seymour Butz
Besides, I don't know of anyone saying that col 79 "pulled" the building down with it. You're making up that argument.
Originally posted by Seymour Butz
So if your theory about thermate in the towers holds water in your eyes, then unbraced ext columns should too.
Originally posted by Griff
Originally posted by Newtons.Bit
I don't follow. Could you explain how a connection would not fail from the member having a thermal expansion of roughly 3 inches?
It depends on what connection you are talking about.
If it is the beam to girder connection, the force is acting directly through the connection so no shearing. The connections would become in tension once the beam starts to cool and retract though as seen in the Cardington tests.
If we are talking about the girder to column connections, we are talking about shear as well due to the beams pushing against the girder perpendicular to the connections which would also cause moments to develope in the connections. Which, I have stated is possible to shear the connection. Depending on strength and bracing of the girders ect.
Disclaimer: This is all opinion so far as I haven't hardly done any calculations.
[edit on 9/4/2008 by Griff]