A-12 Avenger II
Plans for the Navy's A-12 combat aircraft called for incorporating more advanced stealthy characteristics than were used in the F-117A, as well as
significantly greater payload capabilities. The Navy's A-12 Avenger Advanced Technology Aircraft (ATA) was slated to replace current A-6s on aircraft
carriers in the mid-1990's.
But on 7 January 1991, Secretary of Defense Richard Cheney canceled the program, in the largest contract termination in DoD history. By one estimate
the A-12 had become so expensive that it would have consumed up 70 percent of the Navy's aircraft budget within three years.
The Navy originally planned to buy 620 of the McDonnell Douglas/General Dynamics aircraft, with the Marine Corps purchasing an additional 238 planes.
And the Air Force at one point considered buying 400, at an average cost that was estimated at close to $100 million each. The A-12 was designed to
fly faster and further than the A-6E, and carry a large bomb-load in internal bomb-bays to reduce drag and maintain a low radar cross-section. As with
the Advanced Tactial Fighter (ATF), the A-12 was expected to have greater reliability than current aircraft (double that of the A-6E), and require
half the maintenance manhours.
At first blush, the A-12's performance capabilities would have been in roughly the same class as existing aircraft. The key improvement over existing
aircraft, not inherently obvious when comparing specifications, was stealth. While today's radar can detect existing naval aircraft at a range of 50
miles, the A-12 was designed to remain undetected until approximately 10 miles away. This would result in significant operational and survival
benefits for the A-12 since defenders would have little opportunity to engage the aircraft once detected so close to the target. The A-12's reduced
radar cross section would have been derived, in part, from carrying its ordnance internally. While the top speed of the more visible F/A- 18 and A-6
would be significantly reduced by the drag induced by external weapons carriage, the internal weapons bay on the A-12 would provide no impediment to
speed.
The A-12 proved to be the most troubled of the new American stealth aircraft in large part because of problems found in the extensive use of
composites in its structure. These composites did not result in anticipated weight savings, and some structural elements had to be replaced with
heavier metal components. The weight of each aircraft exceeded 30 tons, 30% over design specification, and close to the limits that could be
accommodated on aircraft carriers. The program also experienced problems with its complex Inverse Synthetic Aperture Radar system, as well as delays
in its advanced avionics components.
The full scope of these problems were not appreciated at the time of Defense Secretary Cheney's Major Aircraft Review, which slowed the production
rate and dropped 238 Marine Corps aircraft, leaving the original total Navy buy of 620 aircraft. Cheney also decided to delay for over 5 years the Air
Force buy (from 1992 to 1998), which was decoupled from the Navy project. Subsequently, the A-12 contractors revealed that the project faced serious
engineering problems and a $2 billion cost overrun, which would delay the first flight by over a year, to the fall of 1991, and raised the unit cost
substantially.
According to the 1990 administrative inquiry conducted for the Secretary of the Navy, the cost performance data from the A-12 contractors clearly
indicated significant cost and schedule problems. The results of an oversight review of the cost performance reports disclosed that the A-12 contract
would probably exceed its ceiling by $1 billion. However, neither the contractors nor the Navy program manager relied upon this data; instead, they
used overly optimistic recovery plans and schedule assumptions. The inquiry concluded that the government and contractor program managers lacked the
objectivity to assess the situation and they disregarded financial analysts who surfaced the problems.
The U.S. Navy on January 7, 1991, notified McDonnell Douglas and General Dynamics Corporation (the Team) that it was terminating for default the
Team's contract for development and initial production of the A-12 aircraft, and demanded repayment of the amounts paid to the Team under such
contracts. The Department of Defense terminated the contract after the contractors failed to deliver a single airplane after receiving more than $2
billion in payments. Instead, the contractors refused to continue with the contract unless they received extraordinary relief in the form of relaxed
terms and extra funds. At the same time, they would or could not assure delivery of an aircraft by a time certain, specify the aircraft's performance
capabilities, or commit to a specific price for the aircraft. The Team filed a legal action to contest the Navy's default termination, to assert its
rights to convert the termination to one for "the convenience of the Government," and to obtain payment for work done and costs incurred on the A-12
contract but not paid to date.
On December 19, 1995, the U.S. Court of Federal Claims ordered that the Government's termination of the A-12 contract for default be converted to a
termination for convenience of the Government. On December 13, 1996, the Court issued an opinion confirming its prior no-loss adjustment and no-profit
recovery order. In an early 1997 stipulation, the parties agreed that, based on the prior orders and findings of the court, plaintiffs were entitled
to recover $1.071 billion. Furthermore, on January 22, 1997, the court issued an opinion in which it ruled that plaintiffs are entitled to recover
interest on that amount.
The government is filing a notice of appeal to the United States Court of Appeals for the Federal Circuit following a decision against it on 20
February 1998 by the United States Court of Federal Claims. The Department of Defense believes that the court's decision in favor of the contractors
is wrong and provides unwarranted relief from a failure to produce the aircraft for which the contractors are fully responsible. The Federal Claims
Court decision was fully expected based upon earlier rulings by the trial judge; the government has made clear its belief that those earlier rulings
were fundamentally flawed. The court's decision concludes the protracted trial phase of this case and will allow the appellate phase to begin.
www.geocities.com...
www.geocities.com...
www.geocities.com...
[Edited on 1-9-2003 by quaneeri]