It looks like you're using an Ad Blocker.
Please white-list or disable AboveTopSecret.com in your ad-blocking tool.
Thank you.
Some features of ATS will be disabled while you continue to use an ad-blocker.
Originally posted by Rotator
Just a wild guess, the work being done by the suspicious workers required a power down. Happens from time to time in big buildings.
GW: You've previously stated that on the weekend of September 8 and 9, 2001, there was a "power down" condition in world trade center Tower 2, the South Tower, and that this power down condition meant there was no electrical supply for approximately 36 hours from floor 50 up. Do you know what time the power-down started?
SF: All systems were shutdown on Saturday morning and the power down condition was in effect from approximately 12 noon on Saturday September 8, 2001.
GW: When did it end?
SF: Approximately 2PM on Sunday 9/9.
GW: How do you know that there was no electricity from floor 50 up, if Fiduciary Trust was on much higher floors -- starting at the 90th floor?
SF: I can't absolutely verify that there was no power on lower floors ... all I can validate is that we were informed of the power down condition, that we had to take down all systems and then the following day had to bring back up all systems ...
In 24 days, CDI's 12 person loading crew placed 4,118 separate charges in 1,100 locations on 9 levels of the structure. Over 36,000 ft. of detonating cord and 4,512 non-electric delay devices were installed in CDI's implosion initiation system. As the implosion required the detonation of a total of 2,728 lb. of explosives, CDI implemented 36 "primary delays" and an additional 216 “micro-delays" in the implosion initiation sequence in an attempt to keep detonation overpressure to a minimum.
Start adding bro, cause right now you are selectively picking stuff you think you can de-bunk cause of what some government hack on a web site said...
Originally posted by Swampfox46_1999
No, its me picking things that I dont have to spend all night typing in language you can understand.
Originally posted by ANOK
Originally posted by Rotator
Just a wild guess, the work being done by the suspicious workers required a power down. Happens from time to time in big buildings.
Exactly, that's why it would be relatively easy for a trained team to rig the towers under the guise of maintenance of some kind.
There is a vid with a guy talking about the noise from the floor above him, when he checked and the floor was totaly empty. He talked about a lot of dust being everywhere also, is that the same vid?
I can't find it right now there are so many, my bookmarks list is loooong....
Originally posted by Rotator
Just a wild guess, the work being done by the suspicious workers required a power down. Happens from time to time in big buildings.
Originally posted by Wizard_In_The_Woods
Dear DJMessiah:
Power downs were needed to plant the really big stuff.
1. The explosives for the “impact crash holes”.
2. To position naphthalene IED simulator devices to mimic the plane explosions
3. To place smoke generators and their liquid reservoirs
The thermate cutting charges were placed over much longer periods of time (months).
Greetings,
The Wizard In The Woods
Originally posted by DJMessiah
but why would it happen during work hours, and not at a time where most employees are gone.
Originally posted by lizziex3
Sorry but it would take WAY more than two days to put charges in giant buildings like WTC.
Originally posted by lizziex3
Sorry but it would take WAY more than two days to put charges in giant buildings like WTC.