You do need to trace with polylines along the bottom of the pile - along the ground transition. That will give you an accurate volume.
And i found out you need at least 3 control points that are visible in the survey. You can manually enter them in the ray editor
The Control points are not mandatory, the software runs with out them. But if accuracy is mandatory, then you will need them